Busy Project Time (2).........
So, It's January 2009 and not much has changed, it's still busy project time. Unsurprisingly the server migration which absolutely, totally HAD to be completed by the end of December 2008 wasn't. How the project manager expected 79 servers and a lot of filer data to be moved in less than three months was beyond me but as with so many projects here the project managers are under the thumb from higher ups to deliver so often the way they do this is to pass on only good news to the higher ups whilst pressurising the staff to do the job no matter the cost...
Still, as the company is being taken over there is hope that this will change. Time will tell. With a little luck I'll be back blogging my normal nonsense very soon.